Awarded
Remedial Works to Princess Pier, Torquay
£112,291
works
Contract Details
- Tender Value
- £300,000
- Stage
- Awarded
- Published
- Awarded
Timeline
Awarded
Disclosed
Start
End
Description
The project aspires to reinstate all fire-damaged elements to return the pier to as-existing condition prior to a vessel fire event in June 2022 Princess Pier is an important public amenity. Its ongoing partial or whole closure presents risk to public perception of Torbay in particular at its peak holiday period, and restricts use and enjoyment in connection with pleasure and other vessel berthing.
Related Contracts
From This Buyer
From This Supplier
- TPL9224 Torquay Pavilion - Opening Up Works
£462,000 ·
- Repairs to Meadfoot Sea Wall
£50,000 ·
- Unit 2, Wren Park, Torquay
£204,600 ·
- St Cuthbert Mayne Remodelling
£1,525,000 ·
In This Category
Ref: 845d6056-f53f-4d49-adf8-864f708bcde6-563114 · Sourced from Contracts Finder
View source notice