- Public buyer: [Eiffage Kier JV HS2 Main Civils Works, Lots C2 &amp; C3](/buyers/eiffage-kier-jv-hs2-main-civils-works-lots-c2-c3/contract-awards)
- Published: 12 March 2021
- Planned start: 31 May 2021
- Planned end: 31 July 2023
- Stage: open_tender
- Procurement category: works
- Notice ID: 4434396b-45e2-4d96-915c-b26c2f1c6097-419248
- OCID: ocds-b5fd17-9de04adb-4b2f-4f3a-8066-0f0fa7941255

## Description

EKFB is seeking to appoint a sub-contractor to design, supply, install &amp; commission the temporary cross passage doors for the 3no Green Tunnels\. The purpose of these doors are to isolate the two bores of the Green Tunnel, to provide and preserve independent healthy and safe environments, and to avoid the spread of smoke and fire\. The sliding door will need to withstand a minimum fire resistance of 60 minutes and is required at every emergency opening within the Tunnels, resulting in a total of 18no temporary cross passage doors\. These should cover an approximate area of 1800x2000mm\. The temporary cross passage doors will be supplied and installed on demand, following the pre-cast concrete tunnels' installation \(done by another sub-contractor\), which means these activities will be completed in multiple visits\. The doors should be delivered on site as single units ready to be set up, installed and commissioned Anticipated Programme Greatworth - January 2022 Chipping Warden - September 2021 Wendover - July 2023 Through this expression of interest you will be vetted in accordance with the EKFB prequalification model - for further information visit https://www\.competefor\.com/EiffageKier/ Following receipt of the questionnaire, we will create a short list by assessing capabilities, experience and availability of each supplier\. Upon successful shortlisting you will be invited to tender from the EKFB e-Sourcing platform Market Dojo, EKFB will be using a balanced scorecard approach to its procurement activities - for further information visit the above website\. Kerry Albrighton - Senior Buyer

## Related contract awards

- [EKFB JV - G2S - Green Tunnel Laser Screeding](/contracts/ocds-b5fd17-9450ea23-d3b6-4d5d-aba2-74abc6ea2c4e): Eiffage Kier JV HS2 Main Civils Works, Lots C2 &amp; C3
- [EKFB JV - Temporary Works Design - For Gas Main Protection Slabs \(must be Lloyds registered approved\)](/contracts/ocds-b5fd17-ba40e027-9771-4187-bd6f-452c7c27b96b): Eiffage Kier JV HS2 Main Civils Works, Lots C2 &amp; C3
- [EKFB - Greatworth to Southam- Highway Vehicle Restraint System](/contracts/ocds-b5fd17-d2a7c0bf-278f-40ae-b836-eaf89721f299): Eiffage Kier JV HS2 Main Civils Works, Lots C2 &amp; C3

## Source

[View the original notice on Contracts Finder](https://www.contractsfinder.service.gov.uk/Notice/4434396b-45e2-4d96-915c-b26c2f1c6097-419248)