  1. Planned start
    As published in the notice
  2. Planned end
    As published in the notice

Work description

Program - Works to be carried out between 9 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown].

The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods:

Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown]

Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP.

Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections];

Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion.

Tender period - First Stage Tender - 09 Sept 2022 - 13 October 2022 [5 weeks]

Adjudication & contractor interviews - 14 October - 3 November 2022 [2 weeks]

Second Stage Tender - 4 November 2022 - 15 December 2022. [6 weeks]

Adjudication & contractor appointment - 15 December - 23 December 2022.

Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON

Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest

Additional information: Tender packs can be obtained via Craig Pullen (craig@cpconsulting.org.uk)