Refurbishment and Capital Works Improvement
Contract Details
- Tender Value
- £5,011,966
- Stage
- Open Tender
- Published
Timeline
Description
Program - Works to be carried out between 9 Jan 2023 and 30 Sept 2024 [87 weeks - excluding 2 weeks allowed for the Christmas shutdown]. The works shall be programmed to have several fallow non-working periods to suit the college holidays. During the 88-week construction period, it is anticipated that there will be no work on site for the following periods: Dec 2023 - end of Feb 2024. - 13 weeks [including two-week Christmas shutdown] Location - Campus wide works at Milton College; Woughton Campus West, Leadenhall, MK6 5LP. Works - to replace all windows/doors; fire alarm/compartment improvement works; install ventilation to deep plan rooms; electrical upgrade works; new soffits; facias, guttering/down pipes; re-roofing [flat sections]; Contract/procurement - Two stage contract traditional IFC JCT contract with contractor's design portion. Tender period - First Stage Tender - 09 Sept 2022 - 13 October 2022 [5 weeks] Adjudication & contractor interviews - 14 October - 3 November 2022 [2 weeks] Second Stage Tender - 4 November 2022 - 15 December 2022. [6 weeks] Adjudication & contractor appointment - 15 December - 23 December 2022. Consultant team - Client Representative/Project Manager - Project Management Solutions; Architect/Principal Designer - Devonshire Architects; Structural Consultant - SOLUTION CE; M&E Consultant - Panda CE; Approved Inspector - LEXICON Please contact Craig Pullen (craig@cpconsulting.org.uk) to express an interest Additional information: Tender packs can be obtained via Craig Pullen (craig@cpconsulting.org.uk)
Related Contracts
From This Buyer
- Isles of Scilly Seabird Recovery Project -Operational Plan
£20,000 ·
- Enabling Works Package
£301,722 ·
- IoT South - Bletchley Campus
£11,850,000 ·
- Infrastructure Installation Services
£242,083 ·
From This Supplier
- Expression of Interest: Refurbishment and upgrade of Community Hub roof, refurbishment of 2No. toilet blocks and construction of new toilet facilities
- Apprenticeships Training Dynamic Marketplace
- Taxi and MPV (1-8 seats) Passenger Assistant - Taxi and MPV (1-8 seats) Passenger Assistant
- Taxi and MPV (1-8 seats) Passenger Assistant - Taxi and MPV (1-8 seats) Passenger Assistant
In This Category
- PAHT - ITU Dirty Utility Refurbishment
£52,000 ·
- HD029-25 Peterhouse Road Grimsby
£204,455 ·
- DNWP0019/LOT1B/ WAGR / PIE ILW - Detailed Design
£2,468,738 ·
- PRP318 Glenholme - Refurbishment Works
£1,125,847 ·
Ref: bbd4ee0f-6fb4-44c9-b66c-0f177e67311b-570524 · Sourced from Contracts Finder
View source notice