1997 The provision of: Hawthorn Building - Hot & Cold Water Replacement Phase 3, De Montfort University, Leicester.

Notice details

Published
Category
works
Buyer region
East Midlands

Public buyer

Tender valueNot disclosed

  1. Planned start
    As published in the notice
  2. Planned end
    As published in the notice

Work description

De Montfort University (DMU) seeks to engage a suitably qualified and experienced Contractor to carry out the following works:

The works comprise of the replacement of the existing Hot & Cold Water services. Maintaining hot and cold water supply to critical areas and toilets within the building. Removal of asbestos and pipework. Fire stopping all existing and new penetrations. Making good and decoration to all areas disturbed and affected by proposed works.

The intended key project dates are as follows:- Start on Site - 03/07/2023 Practical Completion - 23/10/2023 Duration - 17 Weeks Full details of the University's requirements can be found in the tender pack.

Additional information: Is a Recurrent Procurement Type? : No