Tender notice
Cranmer Primary School Phases 2 Reception and 3 ARP Unit
Notice details
- Published
- Category
- works
- Buyer region
- London
- Source
- View official notice
Public buyer
Public buyer
London Borough of MertonTender valueNot disclosed
- Planned startAs published in the notice
- Planned endAs published in the notice
Work description
Works comprise Phases 2 and 3 at Cranmer Primary School in relation to the proposed refurbishment of the current Nursery to provide Reception classrooms in addition to adaption of the current Reception to provide a new self contained ARP facility
The works are circa 380K collectively and expected to take 8 weeks commencing two weeks prior to summer holidays commencing The Contractor will be provided with uninterrupted access with Phase 3 commencing once the holidays start on the 24th July. Works must be completed by the 1st September 23