Design & Implementation of a Track Monitoring Plan to facilitate a key temporary solution for the routing of new HV cables which must be connected to buried cables on site at Teesworks. After much exploratory excavation work, it transpires that the excavation required to create a 2m deep Joint Bay, is within the Zone of Influence of the adjacent Network rail tracks. In essence this means that the excavation work required for the project has the ability to compromise the integrity of the railway.