Skip to content

Contract award record

Demolition Framework

Notice details

Published
Category
works
Buyer region
South East

Public buyer and contract winner

Public buyer

MI CONCEPTS LIMITED
awarded to

Contract winner

LAWSON DEMOLITION LIMITED

Award value£10,000,000

  1. Awarded
    Completed
  2. Start
    Completed
  3. End
    Completed

Work description

The procurement covers all necessary activities to fulfil the public portfolio requirements for demolitions, asbestos removal and investigation throughout the contract duration.

A full list of eligible contracting authorities is included as a download link as part of this notice. Works will include environmental appraisals and reports; asbestos reporting and asbestos strip; and all demolition activities including waste removal and recycling (see 'Scope of Works' below).

The Buyer wishes to appoint a selection of contractors in order to cover these requirements. Contractors may tender for certain combinations of lots. Each successful contractor appointed to the Framework will have submitted a schedule of rates, which will be relied upon as a guide when calling off works on an 'as needed' basis, although quotes will be requested. There may also be mini competitions for works between the appointed framework contractors. Appointed suppliers will be expected to work closely and cooperate with contracting authorities, as well as other contractors, and in-house departments or professionals (managers, consultants etc.).

This contract is a multidisciplinary framework agreement. The procurement is a TWO STAGE restricted process, which has a Selection Questionnaire and an Invitation to Tender. Suppliers must first submit a Selection Questionnaire in order to be invited to tender.

*Scope of Works* The works will be divided into lots as grouped below.

-Environmentals: Site Reports and Investigations Ecology and Biodiversity Reports Bat Reports UXO Surveys Radiation Surveys Ground Conditions and Ground Water Others.

-Asbestos Investigation- Sampling Testing Reporting

-Asbestos Removal & Demoiltion Prelims Licensable ACM Removal Non - Licensable ACM Removal Asbestos Disposal Soft Strip Hard Strip Foundations Removal Hard Standing Break Up and Removal Crushing Waste Waste Storage Waste Disposal Reclaim Materials Site Re-Cover

- Project Management

- CDM Coordination

Related awards

Source: Contracts Finder · Notice e752e2a9-ef45-45ab-92e9-29ca3bbff288-191395

View source notice