Daikin Applied Service

Award value£177,896

  1. Awarded
    Completed
  2. Start
    Current phase
  3. End
    Upcoming

Work description

CPI requires a replacement chiller unit on the upper plant deck of The Neville Hamlin Building. The current Chilled water system has a Chilled water tank containing 30% Propyl alcohol and is circulated around the sites plant for cooling capacity. Cooling fluid temperature is set to 7 °C on supply to the plant. CPI have a requirement for the existing two chillers to be repaired, restoring capacity to OEM specification.